Force majeure under French law: what Article 1218 really excuses
Force majeure is at once the most invoked and the most often refused defence in French contract litigation, and foreign businesses regularly overestimate what it covers. Article 1218 of the Civil Code defines it: an event beyond the debtor's control, which could not reasonably be foreseen at the conclusion of the contract, whose effects cannot be avoided by appropriate measures, and which prevents the debtor from performing its obligation. Each word is a condition, the courts apply them strictly, and most invocations fail on one of them: the event was foreseeable, its effects could have been managed, or performance was expensive rather than impossible.
This article sets out the three conditions and the case law that gives them content, the categories of events the courts accept and refuse, the impossibility requirement and its special rules for money debts, the exact effects of a temporary and of a definitive impediment, and the force majeure clauses that let the parties write their own regime.
Is your situation covered by force majeure?
Free · 30 seconds
Is your situation covered by force majeure?
Handled by Petroff Avocats, French registered lawyers · Paris Bar (Toque #C2396)
The three conditions of Article 1218: beyond control, unforeseeable, unavoidable
The statutory definition does not repeat word for word the three criteria the courts used before the reform, exteriority, unforeseeability and irresistibility, but it corresponds to them in substance, and the earlier case law remains transposable:
- An event beyond the debtor's control. The event must not proceed from the debtor's own fault, which by definition lies within its control, and must be both unavoidable and external to it. Illness can qualify, since it is not in principle under the debtor's control (Cass. ass. plén., 14 avr. 2006). By contrast, the freezing of a debtor's bank assets, ordered by public authorities because of the debtor's own activities, is not beyond its control: the debtor placed itself in the legally defined conditions of the freeze (Cass. ass. plén., 10 juill. 2020, n° 18-18.542).
- Not reasonably foreseeable at the conclusion of the contract. An event that could reasonably have been foreseen, and avoided by appropriate measures, is not force majeure: a transporter whose premises were insufficiently secured against theft could not invoke the theft (CA Versailles, 21 avr. 2022, n° 21/03167). Foreseeability is measured against the circumstances and against the debtor's professional competence to foresee the event (Cass. 3e civ., 4 mars 2021, n° 20-14.509).
- Effects unavoidable by appropriate measures. This is the old irresistibility: the debtor must show that no appropriate measure could avert the event's consequences.
A constant of the case law completes the definition: force majeure can never be constituted by the act of the debtor itself, of its employees or of its substitutes (Cass. 3e civ., 25 mars 2021, n° 20-10.654). The debtor must have taken all the measures the circumstances required (Cass. com., 1 oct. 1997, n° 95-12.435). Failures of elementary precaution defeat the defence:
- the party charged with sending an urgent letter, who left on holiday the day after posting it and took no precaution to ensure its timely arrival, could not invoke the postal error that delayed it (Cass. 1e civ., 2 oct. 1984, n° 83-15.331);
- the party who sent a large cheque by ordinary post could not invoke its theft in transit (Cass. civ., 9 mai 1994, n° 91-21.876);
- the party who stored highly inflammable materials without appropriate fire precautions could not invoke the fire (CA Paris, 23 sept. 2021, n° 20/03239).
Even where the event is external, the judges verify the facts concretely: they must examine, for example, whether an armed robbery during a secured transport of mobile-phone products was not an event that could be foreseen (Cass. com., 22 janv. 2013, n° 11-28.083).
What French courts accept and refuse as force majeure: the case law by category
Natural events. Accepted: a tropical storm whose intensity and suddenness were an unforeseeable anomaly for the local climate (Cass. 2e civ., 5 janv. 1994, n° 92-13.853), a hurricane and a storm of exceptional violence, a fire destroying the premises and machines of a business entirely, exceptional snowfalls interrupting the power supply, a delivery delayed by a barge immobilised in ice, and the Covid-19 epidemic, assessed at 17 March 2020 (T. com. Évry, 1 juill. 2020). Refused: heavy rain not shown to be exceptional by the departmental weather records, where the necessary storm precautions had in any event not been taken (Cass. civ., 7 oct. 1987), the collapse of a badly maintained roof in an ordinary storm, the collapse of a disused quarry that had already produced collapses in the same area, and a flood invoked on the sole basis of a natural-disaster order (Cass. 2e civ., 10 déc. 2002).
Violence and war. Accepted: a fire following a burglary with no link to the tenant, a bomb attack, and the partial destruction of a building by terrorist charges where nothing suggested the building was a target (Cass. 3e civ., 28 janv. 1998). Refused: a state of war known to the parties, or foreseeable, at the conclusion of the contract.
Economic circumstances. Almost always refused, because they make performance onerous, not impossible: difficult conditions that made boiler assembly particularly expensive, the refusal of a subcontractor to carry out works in the time demanded, which did not make the debtor's own performance impossible, a supplier's cessation of business which the distributor was bound to anticipate and to cover within the agreed periods, a considerable drop in supplies with a price surge the seller could not show made delivery impossible, an exceptional summer drought where the buyer obtained the same goods from the seller's own supplier, the seller's resistance proceeding from speculation on rising prices (Cass. com., 4 janv. 1980, n° 78-13.978), and the brutal rise of iron prices for a professional of that market (CA Paris, 28 janv. 2009, n° 08/17748). The boundary was drawn by the Cour de cassation itself: where the rise in raw-material costs may have unbalanced the contract's whole economy and stripped the service provider's commitment of any real counterpart, the question of impossibility deserves examination (Cass. com., 29 juin 2010, n° 09-67.369). Where circumstances make performance excessively onerous but still possible, the applicable mechanism is hardship under Article 1195, with its renegotiation and judicial revision remedies, not force majeure.
Strikes. The dividing line is the debtor's grip on the conflict. Accepted: the strike of EDF personnel provoked by government wage decisions the utility could not resist (Cass. ch. mixte, 4 févr. 1983), a printing works that did everything in its power to limit the consequences, a prison guards' strike new in its form, and the rail strike of late 1995, which the SNCF could neither foresee, avoid nor work around (Cass. soc., 11 janv. 2000). Refused: a one-month strike that had ended more than six months before the delivery date, invoked to justify a year of delay (Cass. 1e civ., 16 mai 1977, n° 75-14.575), a dockers' strike that had been threatening for thirteen days, a local strike with an alternative route available, a strike provoked by the employer's own refusal to negotiate salaries, and the EDF strike against a privatisation project (Cass. 1e civ., 30 oct. 2008, n° 07-17.134).
Threats. A franchisor threatened with prosecution for refusal to sell was justified in breaching an exclusive-supply clause (Cass. com., 11 janv. 1984).
Acts of public authority. Accepted: an administrative decision strictly regulating the sale and allocation of the goods owed (Cass. com., 23 juin 1952), an interruption of rail traffic decided by the operator fearing a demonstration, an expropriation forcing a company out of the building housing its business six years into a fifteen-year telephone-installation lease, and an import prohibition unforeseeable for the importer (Cass. com., 1 oct. 1991). Refused: a refusal of planning permission the buyer knew to be likely from an existing prefectoral order (Cass. com., 12 mai 1980), customs difficulties the transporter knew perfectly well, and an expropriation where the termination of the employment contracts flowed from the employer's own choice not to continue the business elsewhere.
| Category | Accepted where | Refused where |
|---|---|---|
| Natural events | Exceptional intensity, unforeseeable for the location | Ordinary weather, poor maintenance, known risks |
| Violence, terrorism | No link to the debtor, target not foreseeable | War known or foreseeable at conclusion |
| Economic circumstances | Only where they make performance truly impossible | Cost increases, supplier failures, price surges |
| Strikes | External, unforeseeable, no workaround | Provoked, long threatened, workaround available |
| Public authority | Unforeseeable prohibitions and requisitions | Measures known or made likely by existing orders |
Performance must be impossible, not merely difficult or expensive
Even an event meeting the three conditions excuses nothing unless it made performance of the obligation absolutely impossible (Cass. 1e civ., 19 déc. 2000, n° 98-14.141), or forced the debtor to violate an obligation incumbent on it. An irresistible cyclone that partly destroyed a hotel did not make resumption of its operation impossible, and therefore did not justify dismissing all the staff (Cass. soc., 12 févr. 2003); an illness that merely makes the exercise of a profession more difficult does not make performance impossible (Cass. 3e civ., 22 janv. 2014, n° 12-28.246).
For money obligations the rule is absolute: the debtor of a contractual sum of money cannot escape its obligation by invoking force majeure (Cass. com., 16 sept. 2014, n° 13-20.306). The event may at most justify a simple delay in payment (Cass. 3e civ., 17 févr. 2010, n° 08-20.943). For obligations that are not pure and simple, the Civil Code distinguishes:
- cumulative obligations: the debtor is released only if the performance of every prestation owed is impossible (C. civ. Art. 1306);
- alternative obligations: impossibility of the chosen prestation releases the debtor (C. civ. Art. 1307-2); a debtor who has not chosen must perform one of the others (C. civ. Art. 1307-3), and is released of a prestation the creditor had chosen where force majeure makes it impossible (C. civ. Art. 1307-4); where all prestations become impossible, release requires force majeure for each (C. civ. Art. 1307-5);
- facultative obligations: the debtor is released as soon as the initially agreed performance becomes impossible (C. civ. Art. 1308).
Does your event pass the Article 1218 test?
Free · 30 seconds
Does your event pass the Article 1218 test?
Handled by Petroff Avocats, French registered lawyers · Paris Bar (Toque #C2396)
The effects of force majeure: suspension or automatic resolution of the contract
The consequences depend on whether the impediment is temporary or definitive (C. civ. Arts. 1218 and 1231-1):
- Temporary impediment: performance of the affected obligations is suspended, unless the resulting delay justifies resolution of the contract. The debtor owes no compensation for the damage the delay causes. When the impediment ends, the contract resumes as it stood: its duration is not extended and no new conditions can be imposed.
- Definitive impediment: the contract is resolved by operation of law (de plein droit), and the debtor is definitively released, with no damages for the consequences of the impediment. Either party may invoke that resolution and, if the other resists, ask the court to record it; the judge does not pronounce the resolution, he acknowledges it.
The resolution operating by effect of the law, its scope is identical whether it results from force majeure or from an automatic termination clause, and each party may rely on it in the same conditions. Release works in both directions: the creditor of the unperformed obligation is also released of its own obligation, and is entitled to restitution of the price paid as consideration for the obligation that was not performed (Cass. com., 26 févr. 2025, n° 23-21.266). Two situations block the release: the debtor had agreed to bear the risk of force majeure, or it had been put on formal notice before the event occurred (C. civ. Art. 1351), subject to proof that the loss would have occurred even on timely performance (C. civ. Art. 1351-1).
Procedurally, the defence keeps its flexibility: a party does not waive force majeure by failing to raise it in the amicable phase and invoking it only in litigation (CA Paris, 4 avr. 2001), but the circumstances of the event must be established, and the judge appraises the constitutive facts sovereignly (Cass. 1e civ., 6 juill. 2022, n° 21-11.310, upholding a Covid-related refund of a deposit under the contract's own clause). The exoneration rules also extend beyond force majeure itself: the debtor is released, in whole or in part, where the damage is due to the victim's own fault (Cass. com., 27 juin 2018, n° 17-14.283), to the unforeseeable and irresistible act of a third party (Cass. 1e civ., 22 avr. 1981, n° 80-10.489), or to a defect of the thing, and compliance with an international sanction can justify non-performance (CA Paris, 16 janv. 2024, n° 22/13548). Where the victim contributed only in part to its own damage, the debtor is partially exonerated (Cass. com., 1 mars 2005; Cass. 1e civ., 1 juill. 2010, n° 09-13.896), but no exoneration is available to a debtor who committed an intentional fault. The burden throughout rests on the debtor invoking the event, and the defence fails where the circumstances of the loss remain undetermined (CA Paris, 29 mai 2013, n° 10/14262).
Force majeure clauses: writing your own regime
The statutory regime applies only in the contract's silence: the contractual arrangement of force majeure belongs to contractual freedom, and international practice runs on it. A well-drafted clause settles the points the statute leaves open:
- the events covered, bearing in mind that a clause merely listing events does not exempt them from judicial review: where the clause did not state that the listed events were automatically force majeure, the judge verified each statutory condition and refused the defence (Cass. com., 23 juin 2021, n° 19-21.919);
- the notification procedure, how and when the debtor must inform the other party that it invokes the event;
- whether both parties or only one may rely on the clause;
- whether the event must be certified by a third party, such as a chamber of commerce of the country where the impediment arose;
- the fate of the contract: suspension, catch-up arrangements, renegotiation or termination, and the treatment of sums already paid;
- whether the exonerating effect is kept or renounced: a debtor may validly agree to bear the risk of force majeure, in which case the event no longer releases it (C. civ. Art. 1351).
On international contracts, the incidence of force majeure is governed by the parties' clauses and, for what they leave open, by the law applicable to the contract, since that law determines the contract's effects; the parties sometimes submit force majeure to a specific law, even the law of the country where the event occurs. Arbitrators, for their part, tend to apply a substantive rule requiring an unforeseeable and irresistible event, without reference to national laws. Contracts exposed to trade measures should say expressly how refusals, reductions or withdrawals of import or export licences, embargoes and exchange-control measures will be treated: these events produce constant disputes where the contract is silent.
Frequently Asked Questions
An event beyond the debtor's control, not reasonably foreseeable when the contract was concluded, whose effects cannot be avoided by appropriate measures, and which makes performance impossible. All conditions must be met, the burden of proving them rests on the debtor who invokes the event, and the judge appraises them sovereignly on the facts.
Almost never: economic circumstances make performance more onerous, not impossible, and the courts have refused cost surges, supplier failures and price rises even for professionals of the market concerned. Performance made excessively onerous but still possible belongs to the hardship rules of Article 1195, not to force majeure.
No. The debtor of a contractual sum of money cannot escape payment through force majeure; at most the event can justify a simple delay. The defence protects obligations whose performance the event makes impossible, not the obligation to pay.
Sometimes. Strikes imposed on the debtor from outside, such as a national rail strike it could neither foresee nor work around, have qualified. Strikes the debtor provoked by its own conduct, strikes long threatened, and strikes with an available workaround have not. The question is always whether the debtor could foresee, avoid or work around the movement.
It is resolved by operation of law: no damages are due for the impediment's consequences, either party can invoke the resolution, and the judge only records it. The creditor is released of its own obligation and recovers the price paid for the obligation that was not performed.
It has been, assessed at 17 March 2020, and the Cour de cassation has upheld a sovereign finding that the progression of the health crisis made performance impossible, justifying the refund of a deposit under the contract's clause. The analysis remains case by case: the date of the contract and the actual impossibility decide.
Yes. The contractual arrangement of force majeure is a matter of contractual freedom: the parties can define the events, the notification procedure, third-party certification and the fate of the contract. But a clause that lists events without stating they are automatically force majeure leaves the judge free to verify every statutory condition.
Yes. A debtor who was on formal notice before the force majeure event occurred is not released, unless it proves the loss would equally have occurred if it had performed on time. Creditors should serve the notice early; debtors should perform before events overtake them.
The business lawyers of Petroff Avocats assess force majeure files against the Article 1218 conditions, draft and negotiate force majeure clauses for domestic and international contracts, and litigate suspension, resolution and restitution disputes. Send us the contract and the facts, and one of our lawyers will come back to you in English within one business day.
Talk to a French business lawyerThis article is for general information only and reflects French law as published at the date shown above. It does not constitute legal advice. Always seek qualified advice before acting.
- C. civ. Art. 1218Defines force majeure and its effects: suspension for a temporary impediment, resolution by operation of law for a definitive oneLégifrance
- C. civ. Art. 1231-1The debtor prevented by force majeure owes no damagesLégifrance
- C. civ. Arts. 1306 to 1308Release rules for cumulative, alternative and facultative obligationsLégifrance
- C. civ. Art. 1351No release where the debtor assumed the risk or was on prior formal noticeLégifrance
- C. civ. Art. 1351-1The debtor on notice is released where the loss would equally have occurred on performanceLégifrance
- Cass. com., 23 juin 1952An administrative decision strictly regulating sale and allocation of the goods was force majeureCour de cassation
- Cass. civ., 7 oct. 1987Rain not shown exceptional, with precautions untaken, is not force majeureCour de cassation
- Cass. 1e civ., 16 mai 1977, n° 75-14.575A strike ended six months before delivery does not justify a year of delayCour de cassation
- Cass. com., 4 janv. 1980, n° 78-13.978A drought is not force majeure where the goods were available and the refusal was speculativeCour de cassation
- Cass. 1e civ., 2 oct. 1984, n° 83-15.331No force majeure where the sender of an urgent letter took no precaution for its timely arrivalCour de cassation
- Cass. civ., 9 mai 1994, n° 91-21.876Theft in transit of a cheque sent by ordinary post is not force majeureCour de cassation
- CA Paris, 23 sept. 2021, n° 20/03239No force majeure where inflammable materials were stored without appropriate precautionsCour de cassation
- Cass. com., 11 janv. 1984A franchisor threatened with prosecution for refusal to sell was justified in breaching the exclusivityCour de cassation
- Cass. com., 1 mars 2005Partial exoneration where the victim contributed in part to its own damageCour de cassation
- Cass. 1e civ., 1 juill. 2010, n° 09-13.896Confirms partial exoneration for the victim's contributory fault; none for an intentional faultCour de cassation
- CA Paris, 29 mai 2013, n° 10/14262Force majeure fails where the circumstances of the loss remain undeterminedCour de cassation
- Cass. com., 12 mai 1980A refusal of planning permission known to be likely at purchase is not force majeureCour de cassation
- Cass. 1e civ., 22 avr. 1981, n° 80-10.489The unforeseeable and irresistible act of a third party exonerates like force majeureCour de cassation
- Cass. ch. mixte, 4 févr. 1983The EDF strike provoked by government wage decisions was force majeureCour de cassation
- Cass. com., 1 oct. 1991An import prohibition unforeseeable for the importer is force majeureCour de cassation
- Cass. 2e civ., 5 janv. 1994, n° 92-13.853A tropical storm of unforeseeable intensity and suddenness was force majeureCour de cassation
- Cass. com., 1 oct. 1997, n° 95-12.435No fault where the debtor took all measures required to avoid the eventCour de cassation
- Cass. 3e civ., 28 janv. 1998Terrorist destruction was force majeure where nothing suggested the building was a targetCour de cassation
- Cass. soc., 11 janv. 2000The late-1995 rail strike, unforeseeable and unavoidable, was force majeureCour de cassation
- Cass. 1e civ., 19 déc. 2000, n° 98-14.141Release requires that performance be made absolutely impossibleCour de cassation
- CA Paris, 4 avr. 2001Force majeure may be invoked for the first time in litigationCour de cassation
- Cass. 2e civ., 10 déc. 2002A natural-disaster order does not by itself establish force majeureCour de cassation
- Cass. soc., 12 févr. 2003A cyclone destroying part of a hotel did not make resuming the business impossibleCour de cassation
- Cass. ass. plén., 14 avr. 2006Only an unforeseeable and irresistible event is force majeure; illness can qualifyCour de cassation
- Cass. 1e civ., 30 oct. 2008, n° 07-17.134The EDF strike against privatisation was not force majeureCour de cassation
- CA Paris, 28 janv. 2009, n° 08/17748A brutal rise of iron prices is not force majeure for a professional of the marketCour de cassation
- Cass. 3e civ., 17 févr. 2010, n° 08-20.943Force majeure can justify a simple delay in paymentCour de cassation
- Cass. com., 29 juin 2010, n° 09-67.369Cost increases stripping the commitment of any real counterpart deserve examination as impossibilityCour de cassation
- Cass. com., 22 janv. 2013, n° 11-28.083Judges must examine whether an armed robbery in secured transport was foreseeableCour de cassation
- Cass. 3e civ., 22 janv. 2014, n° 12-28.246An illness making professional exercise more difficult does not make performance impossibleCour de cassation
- Cass. com., 16 sept. 2014, n° 13-20.306The debtor of a sum of money cannot invoke force majeure to escape paymentCour de cassation
- Cass. ass. plén., 10 juill. 2020, n° 18-18.542The freezing of assets provoked by the debtor's own activities is not beyond its controlCour de cassation
- T. com. Évry, 1 juill. 2020, n° 2020R0092The Covid-19 epidemic qualified as force majeure, assessed at 17 March 2020Cour de cassation
- Cass. 3e civ., 4 mars 2021, n° 20-14.509Foreseeability is assessed against the debtor's professional competenceCour de cassation
- Cass. 3e civ., 25 mars 2021, n° 20-10.654Force majeure supposes a circumstance not imputable to the party in breachCour de cassation
- Cass. com., 23 juin 2021, n° 19-21.919A clause listing events without making them automatic leaves the judge free to verify the conditionsCour de cassation
- CA Versailles, 21 avr. 2022, n° 21/03167A theft made possible by insufficiently secured premises was reasonably foreseeableCour de cassation
- Cass. 1e civ., 6 juill. 2022, n° 21-11.310Sovereign appraisal of the facts; Covid-related impossibility justified a deposit refund under the clauseCour de cassation
- CA Paris, 16 janv. 2024, n° 22/13548Avoiding the application of an international sanction can justify non-performanceCour de cassation
- Cass. com., 26 févr. 2025, n° 23-21.266The creditor released by force majeure recovers the price paid for the unperformed obligationCour de cassation
- Cass. com., 27 juin 2018, n° 17-14.283The victim's fault exonerates the debtor where it has the character of force majeure or is the exclusive causeCour de cassation
Commercial Contracts
Force Majeure Under French
Force majeure is the most invoked and most often refused defence in French contract litigation.
Ask a French LawyerKey Legal References
Defines force majeure and its effects: suspension for a temporary impediment, resolution by operation of law for a definitive one
The debtor prevented by force majeure owes no damages
Release rules for cumulative, alternative and facultative obligations
No release where the debtor assumed the risk or was on prior formal notice
The debtor on notice is released where the loss would equally have occurred on performance
An administrative decision strictly regulating sale and allocation of the goods was force majeure
Rain not shown exceptional, with precautions untaken, is not force majeure
A strike ended six months before delivery does not justify a year of delay
A drought is not force majeure where the goods were available and the refusal was speculative
No force majeure where the sender of an urgent letter took no precaution for its timely arrival
Theft in transit of a cheque sent by ordinary post is not force majeure
No force majeure where inflammable materials were stored without appropriate precautions
A franchisor threatened with prosecution for refusal to sell was justified in breaching the exclusivity
Partial exoneration where the victim contributed in part to its own damage
Confirms partial exoneration for the victim's contributory fault; none for an intentional fault
Force majeure fails where the circumstances of the loss remain undetermined
A refusal of planning permission known to be likely at purchase is not force majeure
The unforeseeable and irresistible act of a third party exonerates like force majeure
The EDF strike provoked by government wage decisions was force majeure
An import prohibition unforeseeable for the importer is force majeure
A tropical storm of unforeseeable intensity and suddenness was force majeure
No fault where the debtor took all measures required to avoid the event
Terrorist destruction was force majeure where nothing suggested the building was a target
The late-1995 rail strike, unforeseeable and unavoidable, was force majeure
Release requires that performance be made absolutely impossible
Force majeure may be invoked for the first time in litigation
A natural-disaster order does not by itself establish force majeure
A cyclone destroying part of a hotel did not make resuming the business impossible
Only an unforeseeable and irresistible event is force majeure; illness can qualify
The EDF strike against privatisation was not force majeure
A brutal rise of iron prices is not force majeure for a professional of the market
Force majeure can justify a simple delay in payment
Cost increases stripping the commitment of any real counterpart deserve examination as impossibility
Judges must examine whether an armed robbery in secured transport was foreseeable
An illness making professional exercise more difficult does not make performance impossible
The debtor of a sum of money cannot invoke force majeure to escape payment
The freezing of assets provoked by the debtor's own activities is not beyond its control
The Covid-19 epidemic qualified as force majeure, assessed at 17 March 2020
Foreseeability is assessed against the debtor's professional competence
Force majeure supposes a circumstance not imputable to the party in breach
A clause listing events without making them automatic leaves the judge free to verify the conditions
A theft made possible by insufficiently secured premises was reasonably foreseeable
Sovereign appraisal of the facts; Covid-related impossibility justified a deposit refund under the clause
Avoiding the application of an international sanction can justify non-performance
The creditor released by force majeure recovers the price paid for the unperformed obligation
The victim's fault exonerates the debtor where it has the character of force majeure or is the exclusive cause

