Article R4532-63
The specific safety plan indicates: 1° The name and address of the contractor; 2° The foreseeable changes in the number of people working on the site; 3° Where applicable, the name and position of the…
20+ full codes, 2,400+ articles translated and updated. Case law linked to every article. Read the actual text before you ask a lawyer about it — free, no login required.
20+
french codes
Fully translated
2,400+
articles in English
Updated regularly
480+
court rulings linked
Per article
Free
full access
No login required
Showing 8321–8330 of 39714 articles for “Art. R 134-5”
The specific safety plan indicates: 1° The name and address of the contractor; 2° The foreseeable changes in the number of people working on the site; 3° Where applicable, the name and position of the…
Where it emerges from the general coordination plan and the prior risk assessment carried out by the company that the measures referred to in Article R. 4532-64 do not need to be taken due to the abse…
Before any work is carried out on the site, the contractor in charge of the main work or the main lot, as well as any contractor called upon to carry out work presenting particular risks included in t…
When drawing up the specific safety plan, the subcontractor shall take into account the information provided by the contractor, in particular that contained in the general coordination plan. He shall…
Where it has not been possible to apply a preventive measure provided for in the plan, the contractor shall indicate on the plan the means of at least equivalent effectiveness that have been implement…
A contractor who has all or part of the contract entered into with the project owner performed by one or more subcontractors must provide the subcontractors with: 1° A copy of the general coordination…
From receipt of the contract signed by the contractor, the subcontractor has at least thirty days to draw up the specific safety plan. This period is reduced to eight days for finishing work in the ca…
Where rescue and evacuation arrangements are covered by the general coordination plan, the specific safety plan may refer to the general coordination plan.
An up-to-date copy of the specific safety plan is kept permanently available on site. The opinions of the occupational physician and the social and economic committee provided for in article R. 4532-6…
The specific safety plan is adapted to the specific conditions of work on the site. To this end, in addition to taking account of the general coordination measures decided by the coordinator and listi…
Avocate au Barreau de Paris
Toque #C2396
15+ Years In French Corporate Practice
English · French · Russian
Ready When You Are
A 20–30 minute call, in English, to scope the engagement. No obligation, no preliminary fee. You will leave the call with a clear view of what the work will cover and what it will cost.
20+ full codes and 2,400+ articles in English, with the key court rulings linked to every article — free to read.
Read MoreA lawyer-reviewed report explaining how the relevant articles apply to your situation, with case-law analysis and next steps.
Read MoreScope your matter with a Paris-Bar avocate — incorporation, contracts, disputes — handled bilingually, end to end.
Read More