Article R4534-32
Spoil or material may only be deposited along a trench more than 1.30 metres deep if it is possible to create a berm at least 40 centimetres wide. This berm must be kept clear of any deposits at all t…
20+ full codes, 2,400+ articles translated and updated. Case law linked to every article. Read the actual text before you ask a lawyer about it — free, no login required.
20+
french codes
Fully translated
2,400+
articles in English
Updated regularly
480+
court rulings linked
Per article
Free
full access
No login required
Showing 1751–1760 of 63520 articles for “Art. IV and V”
Spoil or material may only be deposited along a trench more than 1.30 metres deep if it is possible to create a berm at least 40 centimetres wide. This berm must be kept clear of any deposits at all t…
After a period of rain or frost, the slope of the excavation or trench is examined. If necessary, the shoring is consolidated. The employer shall have this examination carried out by a competent perso…
Trenches and excavations are equipped with the necessary means for rapid evacuation of workers.
Underpinning of foundations may only be carried out in small sections and as and when the shoring, struts or props put in place ensure sufficient safety. However, this requirement does not preclude th…
The slopes and crests of the walls are cleared of any elements that could pose a fall hazard.
The provisions of this chapter do not apply to dismantling, servicing or maintenance work on buildings by destination, including those mentioned in Article 524 of the Civil Code, provided that they ar…
When workers are required to cross a trench more than 40 centimetres wide, means of passage are put in place.
Trenches more than 1.30 metres deep and no more than two-thirds the width of the trench must be shored, braced or propped if their walls are vertical or substantially vertical. The walls of other tren…
When the various components of a shoring system are assembled outside the excavation, the height of these components is at least equal to the total depth of the excavation. To avoid any tipping over o…
Shoring, struts and props may only be removed when effective protective measures have been taken against the risk of rockfall.
Avocate au Barreau de Paris
Toque #C2396
15+ Years In French Corporate Practice
English · French · Russian
Ready When You Are
A 20–30 minute call, in English, to scope the engagement. No obligation, no preliminary fee. You will leave the call with a clear view of what the work will cover and what it will cost.
20+ full codes and 2,400+ articles in English, with the key court rulings linked to every article — free to read.
Read MoreA lawyer-reviewed report explaining how the relevant articles apply to your situation, with case-law analysis and next steps.
Read MoreScope your matter with a Paris-Bar avocate — incorporation, contracts, disputes — handled bilingually, end to end.
Read More