Article R4534-1
The provisions of this chapter apply to building and public works employers whose workers carry out, even on an occasional basis, earthworks, construction, installation, demolition, maintenance, repai…
20+ full codes, 2,400+ articles translated and updated. Case law linked to every article. Read the actual text before you ask a lawyer about it — free, no login required.
20+
french codes
Fully translated
2,400+
articles in English
Updated regularly
480+
court rulings linked
Per article
Free
full access
No login required
Showing 2121–2130 of 36520 articles for “Art. IV & V”
The provisions of this chapter apply to building and public works employers whose workers carry out, even on an occasional basis, earthworks, construction, installation, demolition, maintenance, repai…
In order to prevent spoil, materials, tools or objects of any kind from falling into trenches more than 1.30 metres deep, the trenches must be surrounded by plinths at least 15 centimetres high or hav…
Spoil or material may only be deposited along a trench more than 1.30 metres deep if it is possible to create a berm at least 40 centimetres wide. This berm must be kept clear of any deposits at all t…
After a period of rain or frost, the slope of the excavation or trench is examined. If necessary, the shoring is consolidated. The employer shall have this examination carried out by a competent perso…
Trenches and excavations are equipped with the necessary means for rapid evacuation of workers.
…ll sections and as and when the shoring, struts or props put in place ensure sufficient safety. However, this requirement does not preclude the use of special procedures that provide workers with at l…
The slopes and crests of the walls are cleared of any elements that could pose a fall hazard.
The provisions of this chapter do not apply to dismantling, servicing or maintenance work on buildings by destination, including those mentioned in Article 524 of the Civil Code, provided that they ar…
When workers are required to cross a trench more than 40 centimetres wide, means of passage are put in place.
…o more than two-thirds the width of the trench must be shored, braced or propped if their walls are vertical or substantially vertical. The walls of other trenches, as well as those of excavations or…
Avocate au Barreau de Paris
Toque #C2396
15+ Years In French Corporate Practice
English · French · Russian
Ready When You Are
A 20–30 minute call, in English, to scope the engagement. No obligation, no preliminary fee. You will leave the call with a clear view of what the work will cover and what it will cost.
20+ full codes and 2,400+ articles in English, with the key court rulings linked to every article — free to read.
Read MoreA lawyer-reviewed report explaining how the relevant articles apply to your situation, with case-law analysis and next steps.
Read MoreScope your matter with a Paris-Bar avocate — incorporation, contracts, disputes — handled bilingually, end to end.
Read More